Question: Question 5 You are the project manager for a new training website. You need to perform the perform qualitative risk analysis process. When you have
Question You are the project manager for a new training website. You need to perform the perform qualitative risk analysis process. When you have completed this process, you will produce all of the following as part of the project documents updates output except which one?
A Priority list of risks
B Whats a list of low priority risks
C Probability of achieving time and cost estimates
D Risks grouped by categories