Question: Question 53 (2 points) ( Listen $200,000 Figure 4 PLANNED VALUE (PV) PV EARNED VALUE (EV) $150,000 ACTUAL COST (AC) $100,000 EV $50,000 AC $0

Question 53 (2 points) ( Listen $200,000 Figure 4 PLANNED VALUE (PV) PV EARNED VALUE (EV) $150,000 ACTUAL COST (AC) $100,000 EV $50,000 AC $0 1 2 3 4 5 6 7 8 9 10 11 12 Time (weeks) The orange dot represents the Estimate at Completion (EAC). Will this project finish ahead or behind schedule? Will this project finish above or below its budget