Question: Question 54 MPS Record Lot Size: P=2 Lead Time: 1 weeks Quantity on Hand (Period 0): 0 Week 1 2 3 4 5 6 7
Question 54
MPS Record
Lot Size: P=2
Lead Time: 1 weeks
Quantity on Hand (Period 0): 0
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirements | 100 | 50 | 70 | 40 | 90 | 50 | ||
| Scheduled Receipts | 100 | |||||||
| Projected on-hand inventory | ||||||||
| Planned Receipts | ||||||||
| Planned Order Releases |
Using the data seen above.
What is the planned order release quantity in week 4?
Group of answer choices
a) greater than 50 units but fewer than or equal to 100 units
b) greater than 0 units but fewer than or equal to 50 units
c) greater than 100 units
d) 0 units