Question: MPS Record Lot Size: P = 2 Lead Time: 1 weeks Quantity on Hand ( Period 0 ) : 0 Week 1 2 3 4

MPS Record
Lot Size: P=2
Lead Time: 1 weeks
Quantity on Hand (Period 0): 0
Week 12345678
Gross Requirements 1005070409050
Scheduled Receipts 100
Projected on-hand inventory
Planned Receipts
Planned Order Releases
Using the data seen above.
What is the planned order release quantity in week 4?
Group of answer choices
greater than 0 units but fewer than or equal to 50 units
0 units
greater than 100 units
greater than 50 units but fewer than or equal to 100 units