Question: Question 5a: An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks
Question 5a: An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. (Round your answer to one decimal) Question 8 2 pts Question 5b: What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.) Question 9 2 pts Question 5c : What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round up your answer to the next whole number.)