Question: Question 6 (1 point) Saved Risks on the critical path should be given equal priority than those activities with positive total slack. given lower priority

Question 6 (1 point) Saved Risks on the critical path should be given equal priority than those activities with positive total slack. given lower priority than those activities with positive total slack. given higher priority than those activities with positive total slack. given higher priority than those activities with no total slack