Question: Question 6 1 pts Activity J has an optimistic time estimate of 5 weeks, a most likely time estimate of 8 weeks, and a pessimistic
Question
pts
Activity has an optimistic time estimate of weeks, a most likely time estimate of weeks, and a pessimistic time estimate of weeks. Using PERTCPM an estimate of the variance for activity is:
weeks
weeks
weeks
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
