Question: Question 6 1 pts Activity J has an optimistic time estimate of 5 weeks, a most likely time estimate of 8 weeks, and a pessimistic

Question 6
1 pts
Activity J has an optimistic time estimate of 5 weeks, a most likely time estimate of 8 weeks, and a pessimistic time estimate of 17 weeks. Using PERT/CPM, an estimate of the variance for activity J is: q,
4 weeks
2 weeks
17 weeks
12 weeks