Question: Question 6 1 pts table [ [ Order # , Due Date,Processing Time ] , [ 1 3 9 , day 3 9 ,

Question 6
1 pts
\table[[Order #,Due Date,Processing Time],[139,day 39,12 days],[145,day 57,32 days],[169,day 37,10 days],[146,day 58,30 days]]
If today is day 20, the critical ratio for order number 146 is
1.93
1.45
1.26
 Question 6 1 pts \table[[Order #,Due Date,Processing Time],[139,day 39,12 days],[145,day 57,32