Question: Order # Due Date Processing Time 139 day 39 12 days 145 day 57 32 days 169 day 37 10 days 146 day 58 30

Order # Due Date Processing Time 139 day 39 12 days 145 day 57 32 days 169 day 37 10 days 146 day 58 30 days If today is day 20 and I am scheduling based on Runout Time, I would sequence the orders in this manner Group of answer choices 139, 169, 145, 146 146, 145, 139, 169 169, 139, 145, 146 139, 145, 169, 146