Question: Question 6 1 pts The forward pass in project network calculations determines the: Task duration Earliest times activities can begin Latest times activities must end

Question 6
1 pts
The forward pass in project network calculations determines the:
Task duration
Earliest times activities can begin
Latest times activities must end
Total slack on the project
Earliest times activities must start
 Question 6 1 pts The forward pass in project network calculations