Question: The forward pass in project network calculations determines the: Total slack on the project Task duration Latest times activities must end Earliest times activities can
The forward pass in project network calculations determines the:
Total slack on the project
Task duration
Latest times activities must end
Earliest times activities can begin
Earliest times activities must start