Question: Question 6 1.06 pts The critical path for the network activities shown below is with duration Immediate Activity Duration Predecessors A 10 B 18 6

Question 6 1.06 pts The critical path for the
Question 6 1.06 pts The critical path for the network activities shown below is with duration Immediate Activity Duration Predecessors A 10 B 18 6 A D 4 E 5 B.C, D A-C-E, 21 A-D-E.19 CB-E, 13 A-B-C-D-E, 33 None of the above are true