Question: 1) The critical path for the network activities shown below is with duration Immediate Activity Duration Predecessors A 2 B 4 -- C 6 A,B

 1) The critical path for the network activities shown below is

1) The critical path for the network activities shown below is with duration Immediate Activity Duration Predecessors A 2 B 4 -- C 6 A,B D 1 A,B E 2 B,C.D 2) Activity Preceding Optimistic Probable Pessimistic A 5 11 14 B 3 9 6 10 14 D A, B 5 7 E B 6 11 C 6 8 13 G D. E 2 4 6 H F 3 3 9 a. Calculate the expected duration and variance of each activity. b. Calculate the expected duration and variance of the critical path. C. Calculate the probability that the project will be completed in less than 28 weeks. 3) Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!