Question: QUESTION 6 15 points Save Answer Analysis: A 12 month project is now at 6months and has a cumulative BCws of S150.000, a BCWP of

QUESTION 6 15 points Save Answer Analysis: A 12
QUESTION 6 15 points Save Answer Analysis: A 12 month project is now at 6months and has a cumulative BCws of S150.000, a BCWP of $125,000 and an ACWP of $140,000. Determine the cost and schedule variance at 6 months. Calculate the 6 month SPI and CPL. Also, assuming the budget at completion is $300,000, determine the projected Cost at Completion For the toolbar, press ALT F10 (PC) or ALT+FN+F10 (Mac). Ips Paragraph v Arial 14px I. xx, T The 1 TT 99 22 BB 0)