Question: Draw the full network (Activity on Node style). Calculate the Expected Time for each activity and use CPM method to determine Critical Path. Calculate the

Draw the full network (Activity on Node style).

  1. Draw the full network (Activity on Node style).
  2. Calculate the Expected Time for each activity and use CPM method to determine Critical Path.
  3. Calculate the Activity Variance for the activities along that Critical Path.
  4. What is the probability of completion of the project before 44 weeks?
TIME ESTIMATES (IN WEEKS) IMMEDIATE MOST ACTIVITY PREDECESSOR(S) OPTIMISTIC LIKELY PESSIMISTIC 4 8 10 B A 2 8 24 C A 8 12 16 D 4 6 10 A E B 1 N 3 3 F EC 6 00 20 G E, C 2. 3 4 H F F N 2 2 1 F 6 6 6 D, G, H 4 6 12 K 2 N 3 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!