Question: Question 6 ( 2 points ) In a project network, the critical path is the sequence of activities which has the A ) Most nodes

Question 6(2 points)
In a project network, the critical path is the sequence of activities which has the
A) Most nodes
B) Most events
C) Longest time
D) Most tasks
 Question 6(2 points) In a project network, the critical path is