Question: Question 6 ( 3 points ) Alejandro is planning a software development project and needs to ensure that he cannot finish coding until he finishes

Question 6(3 points)
Alejandro is planning a software development project and needs to ensure that he cannot finish coding until he finishes designing the software architecture. Which type of dependency is this?
Finish-to-Finish (FF)
Finish-to-Start (FS)
Start-to-Start (SS)
Question 6 ( 3 points ) Alejandro is planning a