Question: Question 6 7 pts Here is a deceptively simple project costing problem. I want you to calculate the project costs using the following data: Hourly

Question 6
7 pts
Here is a deceptively simple project costing problem. I want you to calculate the project costs using the following data:
Hourly rate labor: $60 per hour
Hourly rate equipment: $100 per hour
Project duration: 75 hours
G&A overhead costs: 30% of total direct costs
Profit: 25%
What is the profit for this projects?
$3,600
$15.600
$7.500
$4.500
$12,000
$3,900
$19.500