Question: Question 6 options: Using the project data from the previous questions the project can be crashed by 4 days by crashing _ _ _ _

Question 6 options:
Using the project data from the previous questions the project can be crashed by 4 days by crashing _____. Your answer should be in the form X1,Y2,Z3.
The cumulative cost of crashing by 4 days is _____. Your answer should be numeric only with no decimal places