Question: Question 6 The budgeted cost at completion for a certain project is $250,000. To date, the following work packages of the project have been completed:

Question 6

The budgeted cost at completion for a certain project is $250,000. To date, the following work packages of the project have been completed:

Work package

Planned Value (PV)

Actual cost (AC) in $

% Performance (WP)

Earned value

A

?

19 000

100

19 000

B

?

14 000

100

14 000

C

?

4 000

50

7 000

D

?

2 000

10

2000

Q6.1) Find out the Performance measurements of the project

Cost Variance (CV),

Schedule Variance (SV),

Cost Performance Index (CPI)

schedule performance index (SPI).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!