Question: Question 6 The budgeted cost at completion for a certain project is $250,000. To date, the following work packages of the project have been completed:
Question 6
The budgeted cost at completion for a certain project is $250,000. To date, the following work packages of the project have been completed:
| Work package | Planned Value (PV) | Actual cost (AC) in $ | % Performance (WP) | Earned value |
| A | ? | 19 000 | 100 | 19 000 |
| B | ? | 14 000 | 100 | 14 000 |
| C | ? | 4 000 | 50 | 7 000 |
| D | ? | 2 000 | 10 | 2000 |
Q6.1) Find out the Performance measurements of the project
Cost Variance (CV),
Schedule Variance (SV),
Cost Performance Index (CPI)
schedule performance index (SPI).