Question: Question 6 The critical path in a project network is the shortest sequence of activities using the most resources longest ( in terms of duration
Question
The critical path in a project network is the
shortest sequence of activities using the most resources
longest in terms of duration continuous sequence of activities through the network
sequence of activities with the most difficult tasks
most continuous sequence of activities with the most merge activities
shortest continuous sequence of activities through the network