Question: QUESTION 5 The critical path in a project network is the Shortest path through the network. Longest path through the network. Network path with the
QUESTION
The critical path in a project network is the
Shortest path through the network.
Longest path through the network.
Network path with the most difficult activities.
Network path using the most resources.
Network path with the most merge activities.
QUESTION
The assumption that all immediate preceding activities must be complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
Hammock activities.
Concurrent engineering.
A forward pass.
Dissecting.
Laddering.
QUESTION
The delaying of any activity on the will delay the completion of the project by the same amount.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock