Question: QUESTION 6 The Street Project This project involves the tear-out and replacement of 1,500 linear feet of residential road. The activities and rates are listed

QUESTION 6 The Street Project This project

QUESTION 6 The Street Project This project involves the tear-out and replacement of 1,500 linear feet of residential road. The activities and rates are listed in the following table: Activity Total Duration Survey & Layout 3 days Earth Fill 8 days Compaction & Grading 5 days Asphalt 3 days Paint Striping 1 day What is the shortest amount of time this project can be completed if once an activity is started, it runs continuously and without conflicts? Provide a linear balance schedule and a brief explanation that can be seen/easily found somewhere on your file upload. Attach File Browse My Computer Browse Content Collection QUESTION 7 In Reference to the street project What happens to the schedule if you stagger or spread all of the start times of the activities out by 1 day Provide an updated linear balance schedule and a brief explanation that can be seen found easily somewhere on your file upload. Attach File Browse My Computer Browse Content Collection QUESTION 8 In reference to the street project: What happens to the schedule if you need to maintain at least 300'-0" between work crews for each activity? Provide an updated linear balance schedule and a brief explanation that can be seen/found easily somewhere on your file upload. Attach File Browse My Computer Browse Content Collection

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!