Question: Question 6 Using the information contained in the table below, find the following: Draw a precedence diagram Compute the cycle time needed to obtain an
Question 6
Using the information contained in the table below, find the following:
- Draw a precedence diagram
- Compute the cycle time needed to obtain an output of 96 units per day. The process operates 3 shifts per day and 8 hours per shift.
- Determine the minimum number of workstations required
- Assign tasks to workstations using the most following tasks method
- Compute the idle time of the line
- Compute the efficiency of the line
|
| Task Time | Task Must Follow | ||
| Task | (in minutes) | This Task | ||
| A | 3 | |||
| B | 6 | |||
| C | 7 | A | ||
| D | 5 | A, B | ||
| E | 2 | B | ||
| F | 4 | C | ||
| G | 5 | F | ||
| H | 7 | D, E | ||
| I | 1 | H | ||
| J | 6 | E | ||
| K | 4 | G, I, J | ||
|
|
| 50 |
|
|