Question: Question 7 0 / 1 pts task 1 is painting the floor. task 2 is putting the furniture in the room. We must wait for

Question 7
0/1 pts
task 1 is painting the floor. task 2 is putting the furniture in the room. We must wait for the paint to dry before we start task 2. We use a dependency that has this.....
lag
slack
under allocation
fungible
 Question 7 0/1 pts task 1 is painting the floor. task