Question: Question 7 0 / 1 pts task 1 is painting the floor. task 2 is putting the furniture in the room. We must wait for
Question
pts
task is painting the floor. task is putting the furniture in the room. We must wait for the paint to dry before we start task We use a dependency that has this.....
lag
slack
under allocation
fungible