Question: Question 7 ( 1 point ) A specific type of activity - based schedule in which the timing of each activity is determined by working
Question point
A specific type of activitybased schedule in which the timing of each activity is determined by working backward from the project's end date.
WorkBack Schedule
EndtoStart Schedule
Gantt Chart
Reverse Schedule