Question: Question 7 (1 point) Saved Given the following information on crash time and crash time per day, what is the cost of crashing the project

Question 7 (1 point) Saved Given the following

Question 7 (1 point) Saved Given the following information on crash time and crash time per day, what is the cost of crashing the project by 3 days? The only critical path is A-C-E-G: Activity Normal time Crash cost per day 160 50 A B C D E 9 10 5 3 6 3 4 Crash time 8 4 2 2 5 2 2 135 250 242 180 300 F G Your