Question: Question 9 ( 1 point ) Saved Given the following information on crash time and crash time per day, what is the cost of crashing

Question 9(1 point)
Saved
Given the following information on crash time and crash time per day, what is the cost of crashing the project by 2 days? The only critical path is A-C-E-G (assume that it remains the critical path in the crashing procedure):
Activity
Normal time
Crash time
Crash cost per day
A
9
8
80
B
10
4
50
C
5
2
170
D
3
2
250
E
6
5
300
F
3
2
180
G
4
2
300