Question: Question 7 ( 1 point ) Saved When estimating the project schedule, resource constraints should be considered at the same time as sequence constraints. Question
Question point
Saved
When estimating the project schedule, resource constraints should be considered at the same time as sequence constraints.
Question options:
True
False
Question point
Saved
In order to level resources you must:
Question options:
a Identify project peaks
b Delay critical path tasks
c Delay tasks with float
d All of the above
e A and B