Question: Question 7 ( 1 point ) You recently took over a project from another project manager. While reviewing the network diagram, you find that there

Question 7(1 point) You recently took over a project from another project manager. While reviewing the network diagram, you find that there are four critical paths and three near-critical paths. What can you conclude about the project? a The project will likely be completed on time and within budget b The project will require more people and additional budget c The project is at high risk d The project should be terminated.