Question: QUESTION 7 A project consists of five activities with variable time of completion. Given following schedule of activities for this project, Activity Immediate Optimistic Most

QUESTION 7 A project consists of five activities

QUESTION 7 A project consists of five activities with variable time of completion. Given following schedule of activities for this project, Activity Immediate Optimistic Most Probable Pessimistic Predecessor Activities Time (hr) Time (hr) Time (hr) A 2 4 6 B 1 3 5 5 A, B 5 7 9 D A 3 5 7 E B, C 4 6 8 8 What is the expected ES, EF, LS, and LF for activity D? OA. ES = 4 EF = 5 LS = 3 LF = 7 EF = 16 LS = 12 LF = 17 C. ES = 4 EF = 9 LS=4 LF = 9 D. ES = 4 EF = 9 LS = 12 LF = 17 OB. ES = 11

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock