QUESTION 7

A technique used in a PM's project selection tool is also useful when considering quality management. What is this tool?

A. Cost-benefit analysis

B. Parametric estimating

C. Corporate policy

D. Regulatory environmen

t QUESTION 8

One method the PM can use to determine if a project has successfully met a critical milestone is:

A. Quality exit criteria

B. Sign-off by a quality expert

C. ISO 9000 certification

D. Project sponsor sign-off

QUESTION 9

What are the three components utilized when writing the risk plan document? (select three answers)

A. Identification

B. Segmentation

C. Analysis

D. Probability

E. Impact

F. Response

QUESTION 10

Two of the outcomes of risk planning are: (select two responses)

A. Risk acceptance criteria

B. Risk probability and impact matrix

C. Risk register

D. Risk log

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!