Question: Question 7 : Earned value ( 1 0 pts ) During a given TessyYou customer project execution, managers recorded at a given time of the
Question : Earned value ptsDuring a given TessyYou customer project execution, managers recorded at a given time of the project execution some real values as indicated in the following table. IdActivityStatus completionReal durations in daysADevopsCompletedBSpecificationsCompletedCDesignCompletedDDevelopmentIn progressETestingNot startedFDeploymentNot startedGDesign new featuresCompletedHEdit new featuresIn progressIPrintingIn progressJBookbindingNot started KDisplacementNot startedLTrainingNot startedIn taking as activities planification the quantities used in the PERT table, as well as an average cost of resources of $ a day we take into account only resources of type Labor compute at that execution moment the following indicators: The Planned Value PV The Actual Cost AC The Earned Value EV The BAC Budget At Completion The Schedule Variance SV The Cost Variance CV The SPI Schedule Performance Index The CPI Cost Performance Index The PPI Project Performance Index The EBAC Estimated Budget At Completion What can you say about the health of that project?For questions to give answers within a table item value
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
