Question: Question 7 : Earned value ( 1 0 pts ) During a given TessyYou customer project execution, managers recorded at a given time of the
Question : Earned value pts
During a given TessyYou customer project execution, managers recorded at a given time of the
project execution some real values as indicated in the following table.
Id Activity Status
completion
Real durations in days
A Devops Completed
B Specifications Completed
C Design Completed
D Development In progress
E Testing Not started
F Deployment Not started
G Design new features Completed
H Edit new features In progress
I Printing In progress
J Bookbinding Not started
K Displacement Not started
L Training Not started
In taking as activities planification the quantities used in the PERT table, as well as an average
cost of resources of $ a day we take into account only resources of type Labor compute at
that execution moment the following indicators:
The Planned Value PV
The Actual Cost AC
The Earned Value EV
The BAC Budget At Completion
The Schedule Variance SV
The Cost Variance CV
The SPI Schedule Performance Index
The CPI Cost Performance Index
The PPI Project Performance Index
The EBAC Estimated Budget At Completion
What can you say about the health of that project?
For questions to give answers within a table item value
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock