Question: Question 7 Earned Value Reporting You are a manager on a time-constrained project called OKCOMPUTER and you have just received new information at the end
Question 7
Earned Value Reporting
You are a manager on a time-constrained project called OKCOMPUTER and you have just received new information at the end of period 10. Your original baseline plan scheduled budget the PV is below in table 1.
Table 1: Project OKCOMPUTER baseline budget needs
| Project Periods | ||||||||||||||||||||
| ID | DUR | PV | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| A | 2 | $4 | 2 | 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| B | 4 | $12 |
|
| 3 | 3 | 3 | 3 |
|
|
|
|
|
|
|
|
|
|
|
|
| C | 8 | $16 |
|
| 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 |
|
|
|
|
|
|
|
|
| D | 6 | $24 |
|
| 4 | 4 | 4 | 4 | 4 | 4 |
|
|
|
|
|
|
|
|
|
|
| E | 7 | $14 |
|
|
|
|
|
| 2 | 2 | 2 | 2 | 2 | 2 | 2 |
|
|
|
|
|
| F | 4 | $12 |
|
|
|
|
|
|
|
| 3 | 3 | 3 | 3 |
|
|
|
|
|
|
| G | 5 | $10 |
|
|
|
|
|
|
|
|
|
|
|
|
| 2 | 2 | 2 | 2 | 2 |
|
|
At the end of period 10 you have been given this updated information:
- Activities A, B, & D have been completed
- Activities E, C & F are in process
- Activity G has not started.