Question: QUESTION 7 For activities on a project's critical path, a . earliest start time ( ES ) is less than latest start time ( LS
QUESTION
For activities on a project's critical path,
a earliest start time ES is less than latest start time LS
b earliest start time ES equals latest start time LS
c earliest start time ES equals latest finish time LF
d earliest start time ES is greater than latest start time LS
QUESTION
In general, the earliest finish time for an activity is equal to
a earliest start time activity time estimate
b earliest start time activity time estimate
c earliest start time slack time
d earliest start time slack time
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
