Question: QUESTION 7 For activities on a project's critical path, a . earliest start time ( ES ) is less than latest start time ( LS

QUESTION 7
For activities on a project's critical path,
a. earliest start time (ES) is less than latest start time (LS)
b. earliest start time (ES) equals latest start time (LS)
c. earliest start time (ES) equals latest finish time (LF)
d. earliest start time (ES) is greater than latest start time (LS)
QUESTION 8
In general, the earliest finish time for an activity is equal to
a. earliest start time - activity time estimate
b. earliest start time + activity time estimate
c. earliest start time + slack time
d. earliest start time - slack time
 QUESTION 7 For activities on a project's critical path, a. earliest

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!