Question: Question 7 . If we ignore all orders which come after Stallion Apparel, Kibby & Strand has the following time information ( you can get
Question If we ignore all orders which come after Stallion Apparel, Kibby & Strand has the following time information you can get this information when you click on the Production button and go into the Station History tab after Week
Week Resource Productive Time Setup Time Setup Productive Time Total Available Time
Cutting
Cutting
Cutting
Sewing
Sewing
Sewing
Packing
Packing
Packing
Given that idle time is all time that is not productive or setup time, how much is the total idle time for the three resources combined.
Derive the Resource Utilization for each resource shown in table above ie Cutting, Sewing and Packing for the week period. Ignore the Taffys order ie only use information given in the table above
Given that there is only person working in each of these resources, what is the average labor utilization for the whole process for the week period. Ignore the Taffys order ie only use information given in the table above
Given the information in the table above, every production run at each resource requires minutes of setup time. Explain what is setup time.
Provided detailed recommendations how setup time can be possibly reduced. Your answer should include measures discussed in class to reduce setup time
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock