Question: Question 7 The construction project is behind schedule. The Project Board is considering crashing the project for it to be completed earlier. Table 4 shows

Question 7

The construction project is behind schedule. The Project Board is considering crashing the project for it to be completed earlier. Table 4 shows the estimated cost (in thousand dollars) to crash each individual activity.

Required:

  1. Determine the crash cost per month for each of the activities. (Explain the reliable reasons in details)
  2. Determine which activity should be crashed first to reduce one month from the project duration and how much cost will be added to the total project cost. (Explain the reliable reasons in details)
  3. Determine the maximum number of months the project may be crashed and how much cost will be added to the total project cost. (Explain the reliable reasons in details)Question 7 The construction project is behind
Table 4: Estimated cost (in thousand dollars) to crash each individual activity Normal Crashed Duration Duration Activity Predecessor Cost Cost (in months) (in months) A 3 2 3,000 2,000 3,800 B A 4 2 5,500 5,000 A 5 3,500 3 D B, C 6 5,500 5 6,350 E 5 3 5,500 4,500 5,000 F D, E 4 3 5,800

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!