Question: QUESTION 7 The project manager reported that the project has SPI of .83 and CPI of 1.3. How cans the project status BEST described? Project

QUESTION 7 The project manager reported that the
QUESTION 7 The project manager reported that the project has SPI of .83 and CPI of 1.3. How cans the project status BEST described? Project is behind of schedule and over budget Project is behind of schedule and under budget Project is ahead of schedule and over budget Project is ahead of schedule and under budget