Question: Question 7 Which one of the following will decrease the net present value of a project? O Decreasing the project's initial cost at time
Question 7 Which one of the following will decrease the net present value of a project? O Decreasing the project's initial cost at time zero O Increasing the value of each of the project's discounted cash inflows O Increasing the required discount rate O Increasing the amount of the final cash inflow O Moving each cash inflow forward one time period, such as from Year 3 to Year 2 Question 8 Which one of the 1.25 pts 1.25 pts