Question: Using the above table, the earliest start time for activity F is a. 14 weeks b. 17 weeks c. None of these alternatives is correct.

Using the above table, the earliest start time
Using the above table, the earliest start time
Using the above table, the earliest start time for activity F is a. 14 weeks b. 17 weeks c. None of these alternatives is correct. d. 22 weeks e 20 weeks B USE THIS SCENARIO FOR THE NEXT SIX QUESTIONS. A project consists of the following activities: Activity Activity Predecessor Time (Weeks) A 8 12 , 4 D AB E D G E, F 8 10 7 F 9