Question: Question 8 ( 1 point ) In project scheduling, when completing a backward pass, if the next preceding activity has multiple followers, you select the
Question point
In project scheduling, when completing a backward pass, if the next preceding activity has multiple followers, you select
the largest Late Start of all its immediate successor activities to establish the Late Finish.
the smallest Late Start of all its immediate successor activities to establish the Late Finissm.
the largest Early Start of all its immediate successor activities to establish the Late Finish.
the smallest Early Start of all its immediate successor activities to establish the Late Finish.