Question: In backward pass computation in a network diagram, if the next succeeding activity in the backward direction is a merged activity, which Late Start figure

In backward pass computation in a network diagram, if the next

succeeding activity in the backward direction is a merged

activity, which Late Start figure becomes the Late Finish?

Select one:

A. The smallest Late Start figure of all preceding activities

B. The largest Late Start figure of all preceding activities

C. The average Late Start figure of all preceding activities

D. The medium Late Start figure of all preceding activities

E. The mean Late Start figure of all preceding activities

Between projects A and B, project A will be considered a

superior financial undertaking if it has:

Select one:

A. a shorter payback period than project B.

B. a lower average rate of return than project B

C. a lower net present value than project B.

D. a longer payback period than project B

E. All of the above

In network diagramming, a logical relationship in which a

successor activity cannot finish until a predecessor activity has

finished is called?

Select one:

A. Finish-to-finish (FF)

B. Finish-to-start (FS)

C. Start-to-start (SS)

D. Start-to-finish (SF)

E. Dependencies

A technique for estimating the duration or cost of a project in

which an algorithm is used to calculate the cost or duration

based on historical data and project parameters is called.

Select one:

A.Parametric estimating/ratio method

B.Template/Analogous method

C. Phase estimating

D.Range/three point estimating method

E.Consensus methods

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!