Question: In backward pass computation in a network diagram, if the next succeeding activity in the backward direction is a merged activity, which Late Start figure
In backward pass computation in a network diagram, if the next
succeeding activity in the backward direction is a merged
activity, which Late Start figure becomes the Late Finish?
Select one:
A. The smallest Late Start figure of all preceding activities
B. The largest Late Start figure of all preceding activities
C. The average Late Start figure of all preceding activities
D. The medium Late Start figure of all preceding activities
E. The mean Late Start figure of all preceding activities
Between projects A and B, project A will be considered a
superior financial undertaking if it has:
Select one:
A. a shorter payback period than project B.
B. a lower average rate of return than project B
C. a lower net present value than project B.
D. a longer payback period than project B
E. All of the above
In network diagramming, a logical relationship in which a
successor activity cannot finish until a predecessor activity has
finished is called?
Select one:
A. Finish-to-finish (FF)
B. Finish-to-start (FS)
C. Start-to-start (SS)
D. Start-to-finish (SF)
E. Dependencies
A technique for estimating the duration or cost of a project in
which an algorithm is used to calculate the cost or duration
based on historical data and project parameters is called.
Select one:
A.Parametric estimating/ratio method
B.Template/Analogous method
C. Phase estimating
D.Range/three point estimating method
E.Consensus methods