Question: Question 8 ( 1 point ) ( Unit 6 ) The PMBOK ( 2 0 0 8 ) fourth edition identifies a number of cost
Question point
Unit The PMBOK fourth edition identifies a number of cost estimating tools and techniques. During project selection and the approval stage, rough estimates are obtained using both the and methods.
parametric and vendor bid
analogous and parametric
bottomup and vendor bid
analogous and vendor bid