Question: Question 8 1 pts Based on the CPM network in the previous problems, what is the slack in days associated with task T4? Question 9

Question 8 1 pts Based on the CPM network in the
Question 8 1 pts Based on the CPM network in the
Question 8 1 pts Based on the CPM network in the previous problems, what is the slack in days associated with task T4? Question 9 1 pts Based on the CPM network in the previous problems, what is the late start in days for task T6? 12 6 T4 4 T6 6 1 2 Task 3 T1 4 T2 5 T3 6 T4 7 TS 8 T6 9 17 10 11 Precident Dur, days None 4 T1 6 T1 8 T2, T3 4 T2, T3 7 T4 6 T4, TS 8 T1 4 13 8 T5 7 T7 8