Question 10 1 pts Based on the CPM network in the previous problems, if you reduced the duration of task T3 by two days. How much would it reduce the overall project duration in days? 00 1 4 3 2 T2 6 T4 4 T6 6 Precident None T1 T1 T2, T3 T2, T3 T4 T4, T5 1 2 Task 3 11 4 T2 5 T3 6 T4 7 TS 8 T6 9 17 10 11 12 13 Dur, days 4 6 8 4 7 T1 4 6 T3 8 TS 7 17 8 8 16 17 18 19 20 21 22 23 24