Question: Question 8 1 pts Your team's project has fallen slightly behind schedule and will incur late penalties unless the project can be brought back on
Question
pts
Your team's project has fallen slightly behind schedule and will incur late penalties unless the project can be brought back on schedule. Which of the following actions would be most appropriate in this situation?
Eliminate noncricalpath activities because they aren't that important.
Renegotiate the deadline with the project sporisoricustomer.
Crash or shorten the diration those actwities on the critical path that are next in line to be completed!.
Crash or short the duration of thase activities on the critical path with the lowest perperiod crashing costs.