Question: Your team's project has fallen slightly behind schedule and will incur late penalties unless the project can be brought back on schedule. Which of the
Your team's project has fallen slightly behind schedule and will incur late penalties unless the project can be brought back on
schedule. Which of the following actions would be most appropriate in this situation?
Group of answer choices
Eliminate noncriticalpath activities because they aren't that important.
Renegotiate the deadline with the project sponsorcustomer
Crash or shorten the duration those activities on the critical path that are next in line to be completed
Crash or short the duration of those activities on the critical path with the lowest perperiod crashing costs.