Question: Question 8 ( 2 points ) The more autonomy and authority the project manager and project team need to be successful, the more appropriate a
Question points
The more autonomy and authority the project manager and project team need to be
successful, the more appropriate a dedicated project team or an
matrix
structure is to manage the project.
weak
dedicated
strong
projectized
balanced