Question: Question 8 8 pts What is the minimum duration for the project shown below? Activity Duration Activity Duration . 7 F 8 B 7 G

Question 8 8 pts What is the minimum duration for the project shown below? Activity Duration Activity Duration . 7 F 8 B 7 G 13 4 H 9 D 8 1 9 E 11 J 7 F D I D G B E H